Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-20-12 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 044 Payment period ending: 05-20-21 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,152,592.68 8,400.00 2. a. Extra Work 3,830,390.51 39,800.60 b. Adustment Comp. 1,784,003.67 -3,045.33 3. Materials on Hand 4. Earned Subject to Retention 31,766,986.86 45,155.27 5. Mobilization 2,870,000.00 0.00 6. Total Work Completed 34,636,986.86 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,626,986.86 45,155.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,155.27