Dept. of Trans. PROGRESS Serial No. Contract No. 06-145-08-12 11-091604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 79% 11-SD-5530 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-20-06 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 133,096.00 31,046.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 133,096.00 31,046.75 5. Mobilization 23,000.00 1,150.00 6. Total Work Completed 156,096.00 7. Deductions 0.00 7,237.87 8. a.Contract Retentions -6,654.80 -1,552.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 149,441.20 37,882.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,882.28