Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-14-40 11-091824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 45% 11-SD-905-R8.6/R11.6 Federal Project: HPLU-6211(71) HPLU-6211(72) HPLU-6211(73) Progress payment No. 16 Payment period ending: 07-20-09 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,029,040.83 2,029,760.59 2.a. Extra Work 1,329,746.07 137,087.87 b. Adjustment Comp. 380,691.28 93,732.50 3. Materials on Hand 863,962.49 -57,049.64 4. Earned Subject to Retention 23,603,440.67 2,203,531.32 5. Mobilization 5,510,000.00 0.00 6. Total Work Completed 28,249,478.18 7. Deductions -29,965.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,083,475.67 2,193,531.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,193,531.32