Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-07-34 11-091834 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 39% 11-SD-905-R5.2/R6.1 Federal Project: SRRA-A905(20) Progress payment No. 09 Payment period ending: 01-20-12 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,216,578.14 1,249,865.72 2.a. Extra Work 373,469.80 79,872.73 b. Adjustment Comp. 96,883.33 11,187.46 3. Materials on Hand 4. Earned Subject to Retention 9,686,931.27 1,340,925.91 5. Mobilization 875,000.00 0.00 6. Total Work Completed 10,561,931.27 7. Deductions -31,076.79 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,530,854.48 1,340,925.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,340,925.91