Dept. of Trans. PROGRESS Serial No. Contract No. 06-265-15-02 11-091894 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 16% 11-SD-125-9.2/9.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-06 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY ROAD 4TH ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,811.69 73,943.67 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 78,811.69 73,943.67 5. Mobilization 24,253.73 24,253.73 6. Total Work Completed 103,065.42 7. Deductions 8. a.Contract Retentions -7,881.17 -7,394.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 95,184.25 90,803.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,803.03