Dept. of Trans. PROGRESS Serial No. Contract No. 04-356-13-37 11-167874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 89% 11-IMP-78-15.3/15.8 Federal Project: ACNH-X025(25) Progress payment No. 09 Payment period ending: 12-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02190 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,010,208.84 534,766.19 2.a. Extra Work 29,951.97 27,670.01 b. Adjustment Comp. 103,674.32 -7,142.72 3. Materials on Hand 4. Earned Subject to Retention 9,143,835.13 555,293.48 5. Mobilization 642,809.00 0.00 6. Total Work Completed 9,786,644.13 7. Deductions -41,945.81 -10,000.00 8. a.Contract Retentions -457,191.76 -27,764.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,287,506.56 517,528.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 517,528.80