Dept. of Trans. PROGRESS Serial No. Contract No. 05-025-09-50 11-167874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 98% 11-IMP-78-15.3/15.8 Federal Project: ACNH-X025(25) Progress payment No. 10 Payment period ending: 01-20-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02190 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,531,068.15 520,859.31 2.a. Extra Work 33,677.23 3,725.26 b. Adjustment Comp. 67,923.04 -35,751.28 3. Materials on Hand 4. Earned Subject to Retention 9,632,668.42 488,833.29 5. Mobilization 642,809.00 0.00 6. Total Work Completed 10,275,477.42 7. Deductions -61,185.64 -19,239.83 8. a.Contract Retentions -481,633.42 -24,441.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,732,658.36 445,151.80 10. Reduction Amt to Escrow 11. Payment to Escrow 481,630.00 12. Net Pymt. this Estimate 445,151.80