Dept. of Trans. PROGRESS Serial No. Contract No. 05-054-13-11 11-167874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 99% 11-IMP-78-15.3/15.8 Federal Project: ACNH-X025(25) Progress payment No. 11 Payment period ending: 02-20-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02190 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,679,029.85 147,961.70 2.a. Extra Work 37,749.84 4,072.61 b. Adjustment Comp. 67,922.40 -0.64 3. Materials on Hand 4. Earned Subject to Retention 9,784,702.09 152,033.67 5. Mobilization 642,809.00 0.00 6. Total Work Completed 10,427,511.09 7. Deductions -46,490.64 14,695.00 8. a.Contract Retentions -489,235.10 -7,601.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,891,785.35 159,126.99 10. Reduction Amt to Escrow 11. Payment to Escrow 489,230.00 12. Net Pymt. this Estimate 159,126.99