Dept. of Trans. PROGRESS Serial No. Contract No. 03-205-08-32 11-172824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 36% 11-SD-56-1.8/6.6 Federal Project: NONE Progress payment No. 13 Payment period ending: 07-20-03 F C I CONSTRUCTORS INC W R CONNELLY INC JOINT VENTURE 2585 BUISINESS PARK DRIVE VISTA CA 920838831 Escrow No. 01966 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,065,300.43 1,222,572.20 2.a. Extra Work 260,017.32 16,803.69 b. Adjustment Comp. 412,000.00 412,000.00 3. Materials on Hand 416,321.24 104,260.07 4. Earned Subject to Retention 14,153,638.99 1,755,635.96 5. Mobilization 3,800,000.00 0.00 6. Total Work Completed 17,537,317.75 7. Deductions -724.14 10,724.14 8. a.Contract Retentions -752,013.69 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,200,901.16 1,766,360.10 10. Reduction Amt to Escrow 11. Payment to Escrow 752,010.00 12. Net Pymt. this Estimate 1,766,360.10