Dept. of Trans. PROGRESS Serial No. Contract No. 03-266-13-31 11-172824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 50% 11-SD-56-1.8/6.6 Federal Project: NONE Progress payment No. 15 Payment period ending: 09-20-03 F C I CONSTRUCTORS INC W R CONNELLY INC JOINT VENTURE 2585 BUISINESS PARK DRIVE VISTA CA 920838831 Escrow No. 01966 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,379,027.01 2,019,434.01 2.a. Extra Work 584,244.88 118,446.53 b. Adjustment Comp. 493,788.17 81,788.17 3. Materials on Hand 494,756.38 73,935.50 4. Earned Subject to Retention 17,951,816.44 2,293,604.21 5. Mobilization 3,800,000.00 0.00 6. Total Work Completed 21,257,060.06 7. Deductions -10,724.14 -10,000.00 8. a.Contract Retentions -897,590.82 -114,680.21 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,843,501.48 2,168,924.00 10. Reduction Amt to Escrow 11. Payment to Escrow 897,590.00 12. Net Pymt. this Estimate 2,168,924.00