Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-033-10-46 11-172824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 52% 11-SD-56-1.8/6.6 Federal Project: NONE Progress payment No. 20 Payment period ending: 01-20-04 F C I CONSTRUCTORS INC W R CONNELLY INC JOINT VENTURE 2585 BUISINESS PARK DRIVE VISTA CA 920838831 Escrow No. 01966 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,479,890.33 387,370.20 2.a. Extra Work 903,894.25 -1,441.50 b. Adjustment Comp. 802,788.17 0.00 3. Materials on Hand 349,104.00 0.00 4. Earned Subject to Retention 24,535,676.75 385,928.70 5. Mobilization 4,000,000.00 0.00 6. Total Work Completed 28,186,572.75 7. Deductions -20,724.14 0.00 8. a.Contract Retentions -1,226,783.84 -19,296.44 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,288,168.77 366,632.26 10. Reduction Amt to Escrow 11. Payment to Escrow 1,226,780.00 12. Net Pymt. this Estimate 366,632.26