Dept. of Trans. PROGRESS Serial No. Contract No. 04-356-13-37 11-172824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-56-1.8/6.6 Federal Project: NONE Progress payment No. 33 Payment period ending: 12-20-04 F C I CONSTRUCTORS INC W R CONNELLY INC JOINT VENTURE 2585 BUISINESS PARK DRIVE VISTA CA 920838831 Escrow No. 01966 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,818,841.38 113,895.00 2.a. Extra Work 2,094,734.74 38,005.24 b. Adjustment Comp. 3,816,061.16 0.00 3. Materials on Hand 4. Earned Subject to Retention 42,729,637.28 151,900.24 5. Mobilization 4,000,000.00 0.00 6. Total Work Completed 46,729,637.28 7. Deductions -31,404.83 -10,000.00 8. a.Contract Retentions -2,136,481.86 -7,595.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,561,750.59 134,305.23 10. Reduction Amt to Escrow 11. Payment to Escrow 2,136,480.00 12. Net Pymt. this Estimate 134,305.23