Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-13-54 11-172894 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 44% 11-SD-56-2.2/6.2 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-20-05 VALLEY CREST LANDSCAPE DEVELOPMENT INC 8450 MIRAMAR PLACE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,469,017.01 203,804.80 2.a. Extra Work 68,457.29 51,586.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,537,474.30 255,391.35 5. Mobilization 174,291.75 0.00 6. Total Work Completed 1,711,766.05 7. Deductions 8. a.Contract Retentions -76,873.72 -5,516.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,634,892.33 249,874.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,874.39