Dept. of Trans. PROGRESS Serial No. Contract No. 02-052-15-13 11-1734U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 20% 11-IMP-98-R0.3/R56.9 Federal Project: AC-P098(20) STP-P098(20) Progress payment No. 03 Payment period ending: 02-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01878 Total Estimate This Estimate 1. Contract Itms Without Mobil. 721,445.26 538,477.26 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 721,445.26 538,477.26 5. Mobilization 29,008.00 29,008.00 6. Total Work Completed 750,453.26 7. Deductions 8. a.Contract Retentions -72,144.53 -53,847.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 678,308.73 513,637.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,637.53