Dept. of Trans. PROGRESS Serial No. Contract No. 01-141-16-12 11-174324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 41% 11-SD-8-R26.4/R32.0 Federal Project: ACIM-008-1(297) Progress payment No. 05 Payment period ending: 05-20-01 T M ENGINEERING 19301 VENTURA BLVD STE 200 TARZANA CA 91356 Escrow No. 01665 Total Estimate This Estimate 1. Contract Itms Without Mobil. 321,521.68 66,881.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 321,521.68 66,881.80 5. Mobilization 154,500.00 0.00 6. Total Work Completed 476,021.68 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -32,152.17 -6,688.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 443,869.51 70,193.62 10. Reduction Amt to Escrow 11. Payment to Escrow 32,150.00 12. Net Pymt. this Estimate 70,193.62