Dept. of Trans. PROGRESS Serial No. Contract No. 01-234-14-56 11-174324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 32% 11-SD-8-R26.4/R32.0 Federal Project: ACIM-008-1(297) Progress payment No. 08 Payment period ending: 08-20-01 T M ENGINEERING 19301 VENTURA BLVD STE 200 TARZANA CA 91356 Escrow No. 01665 Total Estimate This Estimate 1. Contract Itms Without Mobil. 706,605.02 79,284.22 2.a. Extra Work 2,678.05 0.00 b. Adjustment Comp. 1,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 710,783.07 79,284.22 5. Mobilization 195,700.00 0.00 6. Total Work Completed 906,483.07 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -41,015.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 855,467.17 79,284.22 10. Reduction Amt to Escrow 11. Payment to Escrow 41,010.00 12. Net Pymt. this Estimate 79,284.22