Dept. of Trans. PROGRESS Serial No. Contract No. 06-026-08-27 11-183644 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 73% 11-SD-78-10.5/11.6 Federal Project: STPL-5381(18) Progress payment No. 18 Payment period ending: 01-20-06 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING STE 200 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,003,111.35 465,937.40 2.a. Extra Work 186,981.66 56,154.65 b. Adjustment Comp. 3. Materials on Hand 36,008.61 -8,300.00 4. Earned Subject to Retention 7,226,101.62 513,792.05 5. Mobilization 850,000.00 0.00 6. Total Work Completed 8,040,093.01 7. Deductions -20,801.34 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,055,300.28 503,792.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 503,792.05