Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-194-10-01 11-183644 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-78-10.5/11.6 Federal Project: STPL-5381(18) Progress payment No. 35 Payment period ending: 06-01-07 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING STE 200 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,769,705.09 -856.00 2.a. Extra Work 784,200.36 -1,777.12 b. Adjustment Comp. 131,562.63 7,795.76 3. Materials on Hand 4. Earned Subject to Retention 9,685,468.08 5,162.64 5. Mobilization 850,000.00 0.00 6. Total Work Completed 10,535,468.08 7. Deductions -5,908.63 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,529,559.45 162.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162.64