Dept. of Trans. PROGRESS Serial No. Contract No. 04-296-13-08 11-199364 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 85% 11-IMP-111-13.0/22.1 Federal Project: ACNH-P111(65) Progress payment No. 20 Payment period ending: 10-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02117 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,562,223.63 234,733.41 2.a. Extra Work 466,685.94 0.00 b. Adjustment Comp. 243,498.30 15,879.33 3. Materials on Hand 4. Earned Subject to Retention 12,272,407.87 250,612.74 5. Mobilization 630,000.00 0.00 6. Total Work Completed 12,902,407.87 7. Deductions -47,373.84 -2,000.00 8. a.Contract Retentions -613,620.39 -12,530.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,241,413.64 236,082.11 10. Reduction Amt to Escrow 11. Payment to Escrow 613,620.00 12. Net Pymt. this Estimate 236,082.11