Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-07-31 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 0% 9% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 03 Payment period ending: 01-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,095.98 45,620.98 2.a. Extra Work 240.47 240.47 b. Adjustment Comp. 3. Materials on Hand 16,959.84 16,959.84 4. Earned Subject to Retention 76,296.29 62,821.29 5. Mobilization 6. Total Work Completed 59,336.45 7. Deductions -7,336.46 -7,336.46 8. a.Contract Retentions -7,629.63 -6,282.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 61,330.20 49,202.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,202.70