Dept. of Trans. PROGRESS Serial No. Contract No. 01-141-16-12 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 25% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 08 Payment period ending: 05-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,688,662.07 940,941.74 2.a. Extra Work 19,468.22 -274.24 b. Adjustment Comp. 8,445.01 0.00 3. Materials on Hand 0.00 -141,810.48 4. Earned Subject to Retention 1,716,575.30 798,857.02 5. Mobilization 280,545.75 93,515.25 6. Total Work Completed 1,997,121.05 7. Deductions -42,685.69 -10,000.00 8. a.Contract Retentions -171,657.53 -79,885.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,782,777.83 802,486.57 10. Reduction Amt to Escrow 11. Payment to Escrow 171,650.00 12. Net Pymt. this Estimate 802,486.57