Dept. of Trans. PROGRESS Serial No. Contract No. 01-296-14-12 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 47% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 13 Payment period ending: 10-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,598,688.09 746,139.00 2.a. Extra Work 49,416.77 7,541.55 b. Adjustment Comp. 41,271.31 -125.70 3. Materials on Hand 154,318.39 -1,289.40 4. Earned Subject to Retention 5,843,694.56 752,265.45 5. Mobilization 355,357.95 0.00 6. Total Work Completed 6,044,734.12 7. Deductions -42,720.33 -10,000.00 8. a.Contract Retentions -310,771.71 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,845,560.47 742,265.45 10. Reduction Amt to Escrow 11. Payment to Escrow 310,770.00 12. Net Pymt. this Estimate 742,265.45