Dept. of Trans. PROGRESS Serial No. Contract No. 01-355-14-41 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 56% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 15 Payment period ending: 12-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,519,207.89 1,872,815.78 2.a. Extra Work 57,735.72 6,503.29 b. Adjustment Comp. 47,585.39 6,314.08 3. Materials on Hand 277,312.91 -2,730.79 4. Earned Subject to Retention 8,901,841.91 1,882,902.36 5. Mobilization 374,061.00 18,703.05 6. Total Work Completed 8,998,590.00 7. Deductions -62,533.35 -18,613.02 8. a.Contract Retentions -445,092.10 -94,145.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,768,277.46 1,788,847.27 10. Reduction Amt to Escrow 11. Payment to Escrow 445,090.00 12. Net Pymt. this Estimate 1,788,847.27