Dept. of Trans. PROGRESS Serial No. Contract No. 02-081-14-19 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 68% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 19 Payment period ending: 03-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,109,662.34 267,919.03 2.a. Extra Work 96,887.25 19,886.14 b. Adjustment Comp. -79,525.00 4,756.52 3. Materials on Hand 206,707.79 0.00 4. Earned Subject to Retention 14,333,732.38 292,561.69 5. Mobilization 374,061.00 0.00 6. Total Work Completed 14,501,085.59 7. Deductions -166,624.68 -28,038.25 8. a.Contract Retentions -716,686.62 -14,628.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,824,482.08 249,895.35 10. Reduction Amt to Escrow 11. Payment to Escrow 600,000.00 12. Net Pymt. this Estimate 249,895.35