Dept. of Trans. PROGRESS Serial No. Contract No. 02-113-13-11 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 70% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 20 Payment period ending: 04-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,700,367.01 590,704.67 2.a. Extra Work 132,765.14 35,877.89 b. Adjustment Comp. -81,142.96 -1,617.96 3. Materials on Hand 253,843.93 47,136.14 4. Earned Subject to Retention 15,005,833.12 672,100.74 5. Mobilization 374,061.00 0.00 6. Total Work Completed 15,126,050.19 7. Deductions -312,224.43 -145,599.75 8. a.Contract Retentions -750,291.66 -33,605.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,317,378.03 492,895.95 10. Reduction Amt to Escrow 11. Payment to Escrow 600,000.00 12. Net Pymt. this Estimate 492,895.95