Dept. of Trans. PROGRESS Serial No. Contract No. 02-168-14-34 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 82% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 22 Payment period ending: 06-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,181,303.35 62,124.15 2.a. Extra Work 147,521.92 13,920.65 b. Adjustment Comp. -76,842.96 4,300.00 3. Materials on Hand 113,761.27 0.00 4. Earned Subject to Retention 15,365,743.58 80,344.80 5. Mobilization 374,061.00 0.00 6. Total Work Completed 15,626,043.31 7. Deductions -140,606.60 3,787.59 8. a.Contract Retentions -768,287.18 -4,017.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,830,910.80 80,115.15 10. Reduction Amt to Escrow 11. Payment to Escrow 768,280.00 12. Net Pymt. this Estimate 80,115.15