Dept. of Trans. PROGRESS Serial No. Contract No. 02-204-14-18 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 87% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 23 Payment period ending: 07-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,571,015.24 389,711.89 2.a. Extra Work 147,505.26 -16.66 b. Adjustment Comp. -76,842.96 0.00 3. Materials on Hand 0.00 -113,761.27 4. Earned Subject to Retention 15,641,677.54 275,933.96 5. Mobilization 374,061.00 0.00 6. Total Work Completed 16,015,738.54 7. Deductions -148,606.60 -8,000.00 8. a.Contract Retentions -782,083.88 -13,796.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,085,048.06 254,137.26 10. Reduction Amt to Escrow 11. Payment to Escrow 782,080.00 12. Net Pymt. this Estimate 254,137.26