Dept. of Trans. PROGRESS Serial No. Contract No. 02-268-06-50 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 96% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 25 Payment period ending: 09-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,772,997.12 90,888.09 2.a. Extra Work 176,931.66 5,801.83 b. Adjustment Comp. -52,822.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,897,106.28 96,689.92 5. Mobilization 374,061.00 0.00 6. Total Work Completed 16,271,167.28 7. Deductions -137,171.40 -9,088.80 8. a.Contract Retentions -794,855.31 -4,834.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,339,140.57 82,766.63 10. Reduction Amt to Escrow 11. Payment to Escrow 794,850.00 12. Net Pymt. this Estimate 82,766.63