Dept. of Trans. PROGRESS Serial No. Contract No. 02-295-15-25 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 26 Payment period ending: 10-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,818,191.49 45,194.37 2.a. Extra Work 200,538.40 23,606.74 b. Adjustment Comp. -67,275.73 -14,453.23 3. Materials on Hand 4. Earned Subject to Retention 15,951,454.16 54,347.88 5. Mobilization 374,061.00 0.00 6. Total Work Completed 16,325,515.16 7. Deductions -166,434.99 -29,263.59 8. a.Contract Retentions -797,572.71 -2,717.40 b. Unsatisfactory Prog. -2,717.39 -2,717.39 c. Reduction after 95% Comp. 9. Total pay to Contractor 15,358,790.07 19,649.50 10. Reduction Amt to Escrow 11. Payment to Escrow 797,570.00 12. Net Pymt. this Estimate 19,649.50