Dept. of Trans. PROGRESS Serial No. Contract No. 05-144-13-33 11-207914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 33% 11-SD-5-R16.0/R16.6 Federal Project: ACIM-005-1(595) ACST-S163(24) P-S163(24) Progress payment No. 02 Payment period ending: 05-20-05 HANSON SJH CONSTRUCTION P O BOX 639069 SAN DIEGO CA 921639069 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 776,020.61 556,107.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 776,020.61 556,107.34 5. Mobilization 277,500.00 277,500.00 6. Total Work Completed 1,053,520.61 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,043,520.61 833,607.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 833,607.34