Dept. of Trans. PROGRESS Serial No. Contract No. 07-114-07-50 11-224314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 23% 11-SD-5-R36.5/R37.7 Federal Project: ACIM-005-1(605) Progress payment No. 02 Payment period ending: 04-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,156.23 343,371.83 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,156.23 343,371.83 5. Mobilization 475,000.00 475,000.00 6. Total Work Completed 1,117,156.23 7. Deductions -95,842.96 -95,842.96 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,021,313.27 722,528.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 722,528.87