Dept. of Trans. PROGRESS Serial No. Contract No. 00-327-14-35 11-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 7% 11-SD-805-22.6/26.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-00 SHIVA CONSTRUCTION INC 1360 ROSECRANS STREET SUITE E SAN DIEGO CA 92106 Escrow No. 01549 Total Estimate This Estimate 1. Contract Itms Without Mobil. 519,884.30 172,936.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 519,884.30 172,936.90 5. Mobilization 9,500.00 0.00 6. Total Work Completed 529,384.30 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -27,341.42 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 492,042.88 172,936.90 10. Reduction Amt to Escrow 11. Payment to Escrow 27,340.00 12. Net Pymt. this Estimate 172,936.90