Dept. of Trans. PROGRESS Serial No. Contract No. 02-204-14-18 11-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 48% 11-SD-805-22.6/26.1 Federal Project: NONE Progress payment No. 24 Payment period ending: 07-20-02 SHIVA CONSTRUCTION INC 1360 ROSECRANS STREET SUITE E SAN DIEGO CA 92106 Escrow No. 01549 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,180,302.45 3,665.70 2.a. Extra Work 15,471.55 -56.74 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,195,774.00 3,608.96 5. Mobilization 10,000.00 0.00 6. Total Work Completed 1,205,774.00 7. Deductions -9,933.87 1,000.00 8. a.Contract Retentions -59,788.70 -180.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,136,051.43 4,428.51 10. Reduction Amt to Escrow 11. Payment to Escrow 59,600.00 12. Net Pymt. this Estimate 4,428.51