Dept. of Trans. FINAL Serial No. Contract No. 05-276-12-08 11-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-805-22.6/26.1 Federal Project: NONE Progress payment No. 48 Payment period ending: 06-14-04 SHIVA CONSTRUCTION INC 1360 ROSECRANS STREET SUITE E SAN DIEGO CA 92106 Escrow No. 01549 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,265,358.75 0.00 2.a. Extra Work 18,508.71 1,068.27 b. Adjustment Comp. -19,103.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,264,764.46 1,068.27 5. Mobilization 10,000.00 0.00 6. Total Work Completed 1,274,764.46 7. Deductions 8. a.Contract Retentions -63,479.33 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 63,479.33 0.00 9. Total pay to Contractor 1,274,764.46 1,068.27 10. Reduction Amt to Escrow -63,340.00 0.00 11. Payment to Escrow 63,340.00 12. Net Pymt. this Estimate 1,068.27