Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-13-54 11-228704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 39% 11-SD-5-R12.6/R13.4 Federal Project: ACIM-005-1(598) ACNH-S015(14) Progress payment No. 03 Payment period ending: 11-20-05 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,502.72 56,449.72 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 106,502.72 56,449.72 5. Mobilization 72,500.00 72,500.00 6. Total Work Completed 179,002.72 7. Deductions -21,720.87 -9,382.62 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 157,281.85 119,567.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,567.10