Dept. of Trans. PROGRESS Serial No. Contract No. 04-300-08-54 11-228904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 43% 11-SD-5-R14.5/R15.3 Federal Project: ACIM-005-1(597) Progress payment No. 03 Payment period ending: 10-20-04 DALEY CCAC 5370 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 886,290.94 782,990.94 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 886,290.94 782,990.94 5. Mobilization 70,000.00 35,000.00 6. Total Work Completed 956,290.94 7. Deductions -19,920.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 936,370.94 807,990.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 807,990.94