Dept. of Trans. FINAL Serial No. Contract No. 05-314-13-29 11-228904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-5-R14.5/R15.3 Federal Project: ACIM-005-1(597) Progress payment No. 14 Payment period ending: 07-28-05 DALEY CCAC 5370 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,478,199.06 2,209.00 2.a. Extra Work 170,177.34 -1,319.48 b. Adjustment Comp. -20,256.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,628,119.77 889.52 5. Mobilization 70,000.00 0.00 6. Total Work Completed 1,698,119.77 7. Deductions -12,276.48 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,685,843.29 889.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 889.52