Dept. of Trans. PROGRESS Serial No. Contract No. 01-355-15-02 11-229114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 49% 11-SD-8-10.5/R21.8 Federal Project: ACIM-008-1(295) Progress payment No. 09 Payment period ending: 12-20-01 HAZARD CONSTRUCTION COMPANY AND PAVEMENT SPECIALISTS INCORPORATED A JOINT VENTURE P O BOX 229000 SAN DIEGO CA 92192 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,600,812.83 162,827.62 2.a. Extra Work 30,583.24 -1,219.64 b. Adjustment Comp. 3. Materials on Hand 289,361.76 18,361.03 4. Earned Subject to Retention 2,920,757.83 179,969.01 5. Mobilization 570,000.00 0.00 6. Total Work Completed 3,201,396.07 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -183,675.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,287,081.93 169,969.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,969.01