Dept. of Trans. PROGRESS Serial No. Contract No. 02-081-14-19 11-229114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 66% 11-SD-8-10.5/R21.8 Federal Project: ACIM-008-1(295) Progress payment No. 12 Payment period ending: 03-20-02 HAZARD CONSTRUCTION COMPANY AND PAVEMENT SPECIALISTS INCORPORATED A JOINT VENTURE P O BOX 229000 SAN DIEGO CA 92192 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,271,995.49 748,567.42 2.a. Extra Work 88,085.62 11,705.46 b. Adjustment Comp. 16,145.73 16,145.73 3. Materials on Hand 271,000.73 0.00 4. Earned Subject to Retention 4,647,227.57 776,418.61 5. Mobilization 600,000.00 30,000.00 6. Total Work Completed 4,976,226.84 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -232,361.38 -38,820.93 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,004,866.19 767,597.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 767,597.68