Dept. of Trans. PROGRESS Serial No. Contract No. 01-080-16-22 11-229404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 94% 11-IMP-115-21.2/35.2 Federal Project: STP-S115(8) AC-S115(8) Progress payment No. 04 Payment period ending: 03-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01591 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,371,614.55 116,226.12 2.a. Extra Work 16,190.49 4,029.15 b. Adjustment Comp. -46,911.43 -37,391.29 3. Materials on Hand 4. Earned Subject to Retention 2,340,893.61 82,863.98 5. Mobilization 10,000.00 0.00 6. Total Work Completed 2,350,893.61 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -117,044.68 -4,143.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,223,848.93 68,720.78 10. Reduction Amt to Escrow 11. Payment to Escrow 50,000.00 12. Net Pymt. this Estimate 68,720.78