Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-13-13 11-232604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 56% 11-SD-15-M13.1/M16.8 Federal Project: ACNH-015-4(188) I-015-4(188) Progress payment No. 19 Payment period ending: 08-20-04 COFFMAN SPECIALTIES INC 4375 JUTLAND DR STE 260 SAN DIEGO CA 92117 Escrow No. 02144 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,936,637.77 284,887.32 2.a. Extra Work 339,259.22 39,813.96 b. Adjustment Comp. 183,445.77 -3,000.00 3. Materials on Hand 83,238.86 -5,544.28 4. Earned Subject to Retention 11,542,581.62 316,157.00 5. Mobilization 1,647,506.00 0.00 6. Total Work Completed 13,106,848.76 7. Deductions -77,219.80 220,852.80 8. a.Contract Retentions -577,129.08 -15,807.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,535,738.74 521,201.95 10. Reduction Amt to Escrow 11. Payment to Escrow 577,120.00 12. Net Pymt. this Estimate 521,201.95