Dept. of Trans. FINAL Serial No. Contract No. 11-354-15-06 11-232604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-M13.1/M16.8 Federal Project: ACNH-015-4(188) I-015-4(188) Progress payment No. 40 Payment period ending: 10-27-05 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA, SUITE200 SAN DIEGO CA 92126 Escrow No. 02144 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,351,921.79 0.00 2.a. Extra Work 915,726.19 0.00 b. Adjustment Comp. 594,245.16 125,000.00 3. Materials on Hand 4. Earned Subject to Retention 15,861,893.14 125,000.00 5. Mobilization 1,647,506.00 0.00 6. Total Work Completed 17,509,399.14 7. Deductions -82,494.92 0.00 8. a.Contract Retentions -760,043.41 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 760,043.41 0.00 9. Total pay to Contractor 17,426,904.22 125,000.00 10. Reduction Amt to Escrow -760,040.00 0.00 11. Payment to Escrow 760,040.00 12. Net Pymt. this Estimate 125,000.00