Dept. of Trans. PROGRESS Serial No. Contract No. 05-235-13-47 11-2326U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 39% 11-SD-15-M17.3/M19.1 Federal Project: ACNH-015-4(194) I-015-4(194) Progress payment No. 13 Payment period ending: 08-20-05 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,161,578.80 1,108,596.90 2.a. Extra Work 247,579.63 26,968.88 b. Adjustment Comp. 62,349.01 19,955.14 3. Materials on Hand 487,214.53 46,141.90 4. Earned Subject to Retention 9,958,721.97 1,201,662.82 5. Mobilization 1,150,000.00 0.00 6. Total Work Completed 10,621,507.44 7. Deductions -40,123.01 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,068,598.96 1,201,662.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,201,662.82