Dept. of Trans. PROGRESS Serial No. Contract No. 01-080-12-56 11-233004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 72% 11-SD-75-10.8/ .0 Federal Project: NONE Progress payment No. 14 Payment period ending: 03-20-01 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 01222 Total Estimate This Estimate 1. Contract Itms Without Mobil. 256,852.00 858.00 2.a. Extra Work 107,761.45 0.00 b. Adjustment Comp. 9,522.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 374,135.45 858.00 5. Mobilization 6. Total Work Completed 374,135.45 7. Deductions -1,522.66 0.00 8. a.Contract Retentions -18,706.77 -42.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 353,906.02 815.10 10. Reduction Amt to Escrow 11. Payment to Escrow 18,610.00 12. Net Pymt. this Estimate 815.10