Dept. of Trans. PROGRESS Serial No. Contract No. 03-170-14-29 11-234724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 38% 11-SD-15-R4.0/R5.8 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-20-03 SHIVA CONSTRUCTION INC 1360 ROSECRANS ST STE E SAN DIEGO CA 92106 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 266,441.40 59,020.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 266,441.40 59,020.90 5. Mobilization 20,000.00 0.00 6. Total Work Completed 286,441.40 7. Deductions -9,586.06 7,066.54 8. a.Contract Retentions -13,322.07 -2,951.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 263,533.27 63,136.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,136.40