Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-130-14-32 11-234724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-R4.0/R5.8 Federal Project: NONE Progress payment No. 14 Payment period ending: 01-21-04 SHIVA CONSTRUCTION INC 1360 ROSECRANS ST STE E SAN DIEGO CA 92106 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 386,744.70 0.00 2.a. Extra Work 18,651.37 0.00 b. Adjustment Comp. -10,562.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 394,834.07 0.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 414,834.07 7. Deductions -5,600.30 17,331.00 8. a.Contract Retentions -18,148.18 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 18,148.18 0.00 9. Total pay to Contractor 409,233.77 17,331.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,331.00