Dept. of Trans. PROGRESS Serial No. Contract No. 03-203-13-49 11-2348U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 26% 11-SD-15-M18.5/M20.5 Federal Project: ACNH-015-4(187) I-015-4(187) ACST-P056(1) Progress payment No. 07 Payment period ending: 07-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920838831 Escrow No. 02053 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,432,975.72 339,729.12 2.a. Extra Work 142,422.27 42,596.85 b. Adjustment Comp. 120,123.12 -300.00 3. Materials on Hand 4. Earned Subject to Retention 1,695,521.11 382,025.97 5. Mobilization 907,500.00 0.00 6. Total Work Completed 2,603,021.11 7. Deductions -55,000.00 -9,000.00 8. a.Contract Retentions -169,552.11 -38,202.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,378,469.00 334,823.37 10. Reduction Amt to Escrow 11. Payment to Escrow 169,550.00 12. Net Pymt. this Estimate 334,823.37