Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-14-48 11-2348U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 100% 11-SD-15-M18.5/M20.5 Federal Project: ACNH-015-4(187) I-015-4(187) ACST-P056(1) Progress payment No. 20 Payment period ending: 08-20-04 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920838831 Escrow No. 02053 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,399,217.29 636,696.41 2.a. Extra Work 1,202,503.18 142,632.31 b. Adjustment Comp. 464,295.16 25,058.11 3. Materials on Hand 154,883.60 -56,698.30 4. Earned Subject to Retention 10,220,899.23 747,688.53 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 11,276,015.63 7. Deductions -36,400.00 0.00 8. a.Contract Retentions -511,044.96 -37,384.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,883,454.27 710,304.11 10. Reduction Amt to Escrow 11. Payment to Escrow 511,040.00 12. Net Pymt. this Estimate 710,304.11