Dept. of Trans. PROGRESS Serial No. Contract No. 05-235-13-47 11-2348U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-M18.5/M20.5 Federal Project: ACNH-015-4(187) I-015-4(187) ACST-P056(1) Progress payment No. 31 Payment period ending: 08-20-05 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920838831 Escrow No. 02053 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,856,983.70 -52,828.35 2.a. Extra Work 2,246,379.76 127,071.11 b. Adjustment Comp. 912,719.61 -9,644.38 3. Materials on Hand 4. Earned Subject to Retention 15,016,083.07 64,598.38 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 16,226,083.07 7. Deductions -28,297.66 -70.04 8. a.Contract Retentions -750,804.15 -3,229.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,446,981.26 61,298.42 10. Reduction Amt to Escrow 11. Payment to Escrow 750,800.00 12. Net Pymt. this Estimate 61,298.42