Dept. of Trans. PROGRESS Serial No. Contract No. 06-053-14-30 11-2348U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-M18.5/M20.5 Federal Project: ACNH-015-4(187) I-015-4(187) ACST-P056(1) Progress payment No. 37 Payment period ending: 02-20-06 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920838831 Escrow No. 02053 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,875,559.38 4,256.00 2.a. Extra Work 2,701,665.76 -129.12 b. Adjustment Comp. 1,045,789.37 4,470.82 3. Materials on Hand 4. Earned Subject to Retention 15,623,014.51 8,597.70 5. Mobilization 1,210,000.00 0.00 6. Total Work Completed 16,833,014.51 7. Deductions -22,670.04 0.00 8. a.Contract Retentions -781,150.73 -429.89 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,029,193.74 8,167.81 10. Reduction Amt to Escrow 11. Payment to Escrow 781,150.00 12. Net Pymt. this Estimate 8,167.81